Investment options to develop North-South Expressway proposed

The Government has proposed to the National Assembly three options for transforming investment models at sub-projects of the Eastern North-South Expressway for consideration.
Speeding up the constructon of the Eastern North-South Expressway was important to drive economic growth (Photo: baodautu.vn)
Speeding up the constructon of the Eastern North-South Expressway was important to drive economic growth (Photo: baodautu.vn)
In all three options raised, three out of 11 sub-projects which were already decided to be public-funded following the National Assembly’s Resolution No 52/2017 dated November 22, 2017 were proposed to continue to be public-funded.
Those included expressway projects running from Cao Bo (Nam Dinh province) to Bai Vot (Ha Tinh), from Cam Lo (Quang Tri) to La Son (Thua Thien-Hue) and from Nha Trang (Khanh Hoa) to Dau Giay (Dong Nai) and Cau My Thuan 2 (Tien Giang and Vinh Long).
The transformation of investment models was proposed for the remaining eight sub-projects which were previously planned to be implemented following the public-private partnership (PPP) model.
In the first option, all of these eight sub-projects were proposed to transform to public-funded.
Speeding up disbursement of public investment was identified as one of the key solutions to accelerate post-pandemic economic growth. The North-South Expressway was a prioritised infrastructure project to speed up disbursement of public investment and create a driver for growth.
In this option, the Ministry of Transport estimated that total capital worth nearly VND99.5 trillion (US$4.3 billion) would be needed. The State budget already allocated VND55 trillion for the Eastern North-South Expressway project under Resolution No 52/2017 and the Government proposed to add the rest in the 2021-25 public investment plan.
In the second option, five out of eight sub-projects would be transformed from PPP to public-funded, including four pressing projects running from Mai Son to National Highway 45 (63km), from National Highway 45 to Nghi Son (43km), from Nghi Son to Dien Chau (50km) and Phan Thiet – Dau Giay (99km) and one project from Vinh Hao to Phan Thiet which had not attracted the interest of any investors.
The other three, including Dien Chau – Bai Vot, Nha Trang – Cam Lam and Cam Lam – Vinh Hao, which already attracted several investors, would continue to be implemented following PPP.
In the second option, the total investment was estimated at VND100.25 trillion,VND 88 trillion of which would be funded by the State (VND55 trillion already allocated and a sum worth VND33 trillion needed). A sum worth more than VND12 trillion must be raised from private investment.
In the final option, three were proposed to transform investment models, including projects from Mai Son to National Highway No 45, from Phan Thiet to Dau Giay and from Vinh Hao to Phan Thiet.
The total investment capital was estimated at VND100.8 trillion, of which VND78.4 would come from the State budget.
On May 14, the Government proposed to the National Assembly that all sub-projects of the Eastern North-South Expressway would be transformed from PPP to public-funded to speed up the construction and create a driver for economic growth.
However, the National Assembly Standing Committee did not agree with the proposal, adding that the transformation should be for projects which could not attract PPP investors, those facing difficulties in raising capital and those in pressing need.

Other news